1983
Hitachi first contract with PUB for 6.6KV switchgear
1985
Hitachi first contract with PUB for 22KV switchgear
1986
First consumer 22KV Hitachi Metal clad switchgear substation
1987
Merlin Gerlin 22KV switchgear PUB contract
1989
Hyundai 10MVA transformer PUB contract
1990
Batam industrial Park (BIP) 20KV switchhouse and substation project
Pulau seraya Power Station stage II
1992
First Hitachi 66KV GIS Powergrid contract
1993
Bintan Power House, Bintan industrial park and Bintan resort substation project
1995
Nissin 66KV GIS Powergrid contract
1996
HPSI First 6.6KV and 22KV MCS project in Singapore
1997
Nissin 22KV GIS powerGrid contract
1998
Myanmar 22KV project
Middle East Saudi project
1999
Exxon chemical Olefins Project
2000
Senoko Switchhouse B 230KV GIS replacement
Thailand EGAT Hitachi Digital relay
2001
Move to present premises at Kian Teck
2002
Burnei Mentiri Hitachi 66KV and 11KV GIS project
2004
Hitachi Nippon Steel semiconductor 45MVA transformer duplication work
2005
Powergrid air compressor replacement work
2007
Powergrid 66KV substation maintenance
2008
Install first Hitachi CVIS
Dubai monorail
Technical Agreement with Hitachi to manufacture 22KV MCS under license
2009
Bukom SPPG JAEP 66kV Substation
230kV Mitsubishi GIS maintenance Tuas
2010
Tampines 230kV Alstom GIS Substation
First ILJIN power transformer at Banyan Drive
2011
SPPG Nissin 22kV GIS maintenance
2012
SPPG Nissin 66kV GIS maintenance
Support Hitachi transport group testing at Taiwan (Tao Yuan Metro)
2013
SPPG Rangoon 400kV Substation installation & testing
Tembusu 230kV Siemens Series Reactor Testing & Commissioning
Tembusu 200MVA TR testing & commissioning
MAS 22kV Switchgear Supply & Install
2014
Jurong West, Tuas South, Jurong Pier 66kV GIS extension
SPPG 66kV S/S relay modification contract
Helios 3MVA TR supply & Install
Keppel FELS 12MVA TR supply & Install
66kV Mitsubishi GIS maintenance Admiralty, Labrador
230kV Mitsubishi GIS maintenance Labrador
2015
NTU Lee Kong Chian Medical School Switchgear supply & Install
SPPG RMU Maintenance contract
Soxal UMC Switchgear supply & Install
Bank of China building Switchgear replacement
Soxal GFS Switchgear supply and Install
SPPG 500 units RMU supply & Install
66kV Mitsubishi, GIS Maintenance Labrador
2016
NTU Sports Hall Switchgear & Transformer supply & Install
NTU ESS Switchgear Supply and Install
SPPG 66kV substation extension project
Tuas Power 66kV Switchgear extension project
SPPG SCADA retrofit contract
Meiden 75MVA T/F testing & commissioning
2017
Hitachi 66kV GIS Maintenance (Part 1)
Tuas 400kV Toshiba GIS Maintenance
Protection Relays Modification Work
ABB Shunt Reactor 100MVAR/150MVAR testing & commissioning
2018
NDT185 supply, install & test 75MVA T/F to SP
Woodlands 230kV S/S testing & commissioning
Supply, install & test 66kVAIS 700 panels to SP
2019
Supply, install & test 5 Nos. 50MVAR Shunt Reactor to SP (NDT255)
230kV GIS Maintenance Labrador S/S
66kV GIS Maintenance Labrador S/S
Hitachi 66kV GIS Maintenance (Part 2)
2020
Maintenance of 230/66kV GIS Mitsubishi MCS 39 (SPPG)
Maintenance of 66kV GIS various S/S Hitachi (SPPG)
Supply of 75MVA T/F NDT 254, 288 (SGB) (SPPG)
Protection retrofication EMU 96 (SPPG)
Micron supply & install AIS
Supply & install Toshiba 66kV AIS 700 panels (SPPG)
2021
Maintenance of Melco Switchgears (MCS39)
Relocation and Re-commissioning for 200MVA 230/66kV, 75MVA 66/22kV Transformer (NDT216)
2022
75MVA Power Transformer, Power Cables, Ancillary Equipment and Accessories (NDT254)
Service and maintenance of 22kv switchgears, 6.6 kv switchgears and transformer at Micron
2023
Maintenance of Nissin 66kV MetalClad Sf6 Gas Insulated Switchgear (GIS)
Ongoing projects